Risk Register

Build and maintain a project or product risk register. Use when asked to create a risk register, identify project risks, build a risk matrix, or document risks and mitigations for a programme. Produces a complete risk register with likelihood/impact scoring, RAG status, ownership, and prioritised mitigations.

Published by @Mohit Aggarwal·0 agent reads / 30d·0 saves·

Risk Register Skill

This skill produces a complete risk register for a project, programme, or product. Output follows standard risk management practice with likelihood × impact scoring, RAG status, a risk heat map, and specific mitigation and contingency plans. Ready to share with a project board, steering committee, or programme office.

Required Inputs

Ask the user for these if not provided:

  • Project or product name
  • Project stage (discovery / delivery / launch / live / programme-level)
  • Key objectives — what is the project trying to achieve?
  • Known risks — anything already on the team's radar (even informal concerns count)
  • Key dependencies — external vendors, teams, systems, or regulatory approvals
  • Deadline or milestone sensitivity — are there hard dates that cannot move?
  • Audience — who will read this? (internal team / executive steering / external board / regulator)

Output Structure


Risk Register: [Project / Product Name]

Project stage: [Discovery / Delivery / Launch / Live / Programme] Version: [1.0] Owner: [PM / Programme Manager / Risk Lead] Last reviewed: [Date] Next review: [Date — recommend weekly during delivery, monthly during discovery] Status: [Active / Archived]


1. Risk Scoring Framework

Likelihood (L)

ScoreLabelDefinition
5Almost certain>80% probability of occurring
4Likely60–80% probability
3Possible40–60% probability
2Unlikely20–40% probability
1Rare<20% probability

Impact (I)

ScoreLabelDefinition
5CriticalProgramme failure, regulatory breach, major financial loss, safety event
4HighSignificant schedule delay (>4 weeks), scope reduction, reputational damage
3MediumModerate delay (1–4 weeks), cost overrun, reduced quality
2LowMinor delay (<1 week), manageable cost increase
1NegligibleMinimal impact, easily absorbed

Risk Score = L × I

ScoreRAGAction
20–25🔴 CriticalImmediate escalation; active management required
12–19🔴 HighOwner-assigned mitigation; weekly review
8–11🟡 MediumMitigation planned; fortnightly review
4–7🟡 LowMonitor; monthly review
1–3🟢 NegligibleAccept; review if context changes

2. Risk Register

IDRiskCategoryLIScoreRAGOwnerStatusMitigationContingencyReview date
R01[Risk description — be specific: "Third-party API may not support required volume, causing X to fail"][Schedule / Technical / Resource / Commercial / Compliance / External][1–5][1–5][L×I]🔴/🟡/🟢[Name][Open / Mitigating / Closed][What are we doing to reduce likelihood or impact?][What do we do if it happens?][Date]
R02[...][...][...][...][...][...][...][...][...][...][...]

3. Risk Categories — Common Risks by Type

Use these to prompt risk identification. Add, remove, or customise for your project.

Schedule & Delivery

  • Key milestone depends on a dependency that has not confirmed availability
  • Team capacity reduced by planned or unplanned absence during critical period
  • Technical complexity is underestimated — story points consistently overrun
  • External approval (regulator, legal, procurement) takes longer than planned

Technical

  • Integration with a third-party system not yet prototyped or agreed
  • Existing technical debt makes the change harder or riskier than estimated
  • Security or compliance review required before launch has not been scoped
  • Performance under production load untested
  • Key technical knowledge held by one person (single point of failure)

Resource & People

  • Key SME or engineer leaving or unavailable during critical phase
  • Budget not confirmed for Phase 2 of the project
  • Stakeholder sponsor changes role or leaves the organisation
  • Team not yet at full capacity (hiring lag, access issues, onboarding time)

Commercial & Financial

  • Vendor or partner contract not yet signed
  • Cost estimate based on assumptions that have not been validated
  • Revenue or savings case depends on assumptions outside the team's control
  • Currency exposure or exchange rate risk for international projects

Compliance & Regulatory

  • Data privacy impact assessment (DPIA) not yet complete
  • Regulatory approval required and timeline is uncertain
  • GDPR, HIPAA, SOC 2, or sector-specific compliance requirement not yet mapped
  • Legal review of terms of service or contracts pending

Stakeholder & Adoption

  • Key user group has low awareness or motivation to adopt the change
  • Internal resistance from a team that will be affected by the change
  • Executive sponsor not consistently engaged — decisions are slow
  • Communications plan not yet agreed with change management team

External

  • Market or competitive change could undermine the business case
  • Macroeconomic conditions affect budget or priority
  • Supplier or infrastructure provider risk (e.g. cloud provider, hardware)
  • Geopolitical or regulatory environment change

4. Risk Heat Map

Plot risks by likelihood (Y axis) and impact (X axis):

         │  Low     Medium    High    Critical
         │  (1)      (2-3)    (4)      (5)
─────────┼────────────────────────────────────
Almost   │  🟡        🟡       🔴       🔴
certain  │
(5)      │
─────────┼────────────────────────────────────
Likely   │  🟡        🟡       🔴       🔴
(4)      │
─────────┼────────────────────────────────────
Possible │  🟢        🟡       🟡       🔴
(3)      │
─────────┼────────────────────────────────────
Unlikely │  🟢        🟢       🟡       🟡
(2)      │
─────────┼────────────────────────────────────
Rare     │  🟢        🟢       🟢       🟡
(1)      │

[Plot each risk ID on this grid — e.g. R01 lands at L4/I5 = 🔴 Critical]


5. Top Risks — Executive Summary

For steering committee or board-level reporting:

RankRiskScoreRAGOwnerMitigation status
1[Most critical risk — plain English description][X]🔴[Owner][Active / Planned / Not started]
2[...][...]🔴[...][...]
3[...][...]🟡[...][...]
4[...][...]🟡[...][...]
5[...][...]🟡[...][...]

Decisions required from steering:

  • [Any risk that requires budget, scope, or timeline decision to mitigate]

6. Risk Changes Since Last Review

Risk IDChangeDetail
[R03]Score increased[L moved from 2 → 4 — vendor confirmed delay in API availability]
[R07]Risk closed[Legal sign-off received on 12 May]
[NEW]New risk identified[R09 — budget freeze announcement affects Phase 2 funding]

7. Risk Closure Criteria

A risk is closed when:

  • The risk event can no longer occur (e.g. milestone passed, contract signed), OR
  • The residual risk score drops to Negligible (1–3) AND the team formally accepts it, OR
  • The risk has materialised and transitioned to an issue (tracked separately)

Issues log: [Link to issues log — risks that have materialised and are now active problems being managed]


Quality Checks

  • Every risk has a specific owner — not "the team" or "TBD"
  • Mitigations describe what is actively being done — not "monitor and review"
  • Contingency plans exist for all Critical and High risks
  • Risk descriptions are specific — "vendor may be late" is not specific enough; name the vendor and the dependency
  • Register has been reviewed in the last [X] days
  • Closed risks are archived, not deleted — they provide audit trail
  • Risks are distinguished from issues — a risk is something that might happen; an issue is something that has happened

Example Trigger Phrases

  • "Build a risk register for our product launch"
  • "Create a risk matrix for [project name]"
  • "What risks should I document for a data migration project?"
  • "Generate a risk register for our steering committee"
  • "Help me identify and score risks for our Q3 delivery plan"

Anti-Patterns

  • Do not assign risks to "the team" or "TBD" — every risk must have a named individual owner
  • Do not write mitigations as "monitor and review" — mitigations must describe what is actively being done to reduce likelihood or impact
  • Do not delete closed risks — they provide an audit trail; archive them instead
  • Do not confuse risks with issues — a risk is something that might happen; an issue is something that has already happened
  • Do not leave Critical or High risks without a contingency plan — what happens if the mitigation fails must be documented

Bundled with this artifact

1 file

Reference files that ship alongside this artifact. Agents pull these in only when the task needs them.

More on the bench

SKILL0

Rfp Builder

Create Request for Proposals with requirements specifications, evaluation criteria, scoring rubrics, timelines, and compliance requirements

operations+1
0
SKILL0

Okr Builder

Create well-structured OKRs (Objectives and Key Results) for product teams, startups, and individuals. Use when asked to write OKRs, set quarterly goals, define key results, or review existing OKRs. Produces a complete OKR set with objectives, measurable key results, baselines, and a scoring guide.

product-management+2
0
SKILL0

Raci Matrix

Define a RACI matrix for a cross-functional project or process. Use when asked to build a RACI, create a responsibility matrix, clarify ownership across teams, or document decision rights. Produces a complete RACI matrix with role definitions, decision mapping, and a process for resolving conflicts.

product-management+2
0